There is still work going on in the complex. On this page we will keep you informed of the activities per week and what it means for the residents.
Week 5:
Placing glass of the BOG facades
Applying facade cladding end facades
Installing wall cladding in the main entrance area à Nuisance with regard to mobile scaffolding in the entrance area
Placing and mounting steel anchors for facade cladding car ramp (exact date is still unknown)
Week 6:
Main stairs work, the stairs will be closed from Wednesday until Friday.
Applying facade cladding end facades
Sanding concrete columns on the floors for the elevator
Prognosis: Mounting legs for car ramp
Prognosis: Installing ceiling cladding in main entrance area à Nuisance with regard to mobile scaffolding in entrance area